ISIS School of English - 259 Greenwich High Road

An exciting new project in the centre of Greenwich has recently been completed. The project was carried out in two phases.

Phase 1 covered mainly the ground floor, which meant relocating the main central offices of the school into a new area with a frontage. This enabled the operation of the school to continue while the remaining work continued.

Phase 2 involved the removal of the external fabric and replacement with a modern cladding. Internally the 1st and 2nd floors were completely re-designed to meet the school’s requirements and a DDA compliant lift installed along with a energy efficient mechanical and electrical systems.